McKinley Road work completed

Work has been completed on safety improvements to McKinley Road.

The work started Oct. 3 and resulted in an increase to the curve radius on the road from 40 metres to 60 metres, a straightening of part of the road, as well as adding a larger curve at the start of the section along side the adjacent reservoir.

The road also had the the travel lanes widened to 3.5 metres with a one-metre shoulder and precast concrete barriers were installed adjacent to the reservoir. The $458,000 project was completed by OK Excavating and was came in on time and on budget, says the city.

The work was prompted by a serious accident on the road late last year that resulted in a young woman being killed when her car went off the road and into the reservoir.

Prior to that accident there had been numerous other accidents and close calls on the winding stretch of McKinley Road.

 

 

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

Rutland Secondary washroom fire in Kelowna
 
Premier wants municipal pay to be election issue
 
Slocan Valley trail to remain non-motorized
Fraser Street closed as City repairs sewer line
 
Garbage truck catches fire near Summit Lake
 
Kaslo recycling could move to transfer station
A cut above
 
Potential ambassadors gather in Merritt
 
Village voters give Acton another chance

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 1 edition online now. Browse the archives.