Kelowna's Bernard Avenue revitalization ahead of schedule

Two down, one to go.

The second phase of the revitalization of Kelowna's main downtown street, Bernard Avenue, is expected to wrap up either late this week of early next week, more than a month ahead of schedule.

With only road line painting still to be done, the re-opening of the stretch from Abbott Street to Pandosy Street is dependent on the weather, say city officials.

If the rain holds off long enough for crews to paint the lines on the road, vehicles could be driving on the lower stretch of the revamped Bernard Avenue by the weekend.

And while that will make pedestrians, drivers and business owners in the area very happy, it is also welcome news for the company doing the work.

Vernon-based CGL Contracting Ltd was awarded an $11 million contract to do the bulk of the work on the $14 million project and it calls for a $150,000 bonus if the company completed the second phase of three-phase project before the end of May because it was considered the largest and most difficult  phase and the area where the city wanted re-opened to the public as quickly as possible. The contractor has until June 30 to complete the second phase of the revitalization work.

The third phase, from Pandosy Street to St. Paul Street, is scheduled to start just after Labour Day and be complete by the end of November. The first phase, from Richter Street to St. Paul was completed last fall.

The revitalization project includes repair and replacement of utilities under the road surface, as well as repaving, new parking, wider sidewalks, improved lighting, landscaping and new street furniture and decoration all part of creating what City Hall says will be of a more "people-friendly" street.

Additional trees have been planted alongside the road and improvements are also being made to Kerry Park at the foot of Bernard.

The work is part of a major overhaul of the the downtown area, which will also see the construction of a new commercial dock nearby at the foot of Queensway and a new 120-metre long public walking pier just off Kerry Park.

Work has started on the commercial dock and components of the $5.1 million pier are currently being built at a temporary construction facility on the west side of the lake. When complete,the components will be floated into place on the Kelowna side and connected together.

Several small wooden buildings will be built as part of the dock/pier project, the first of which, a ticket booth for the commercial dock, is now up.

The company building the pier and dock, Edmonton-based Westcorp, will maintain and operate it for the next 15 years and plans to build a boutique hotel on the site of the former Willow Inn Hotel at the corner of Mill Street and Queensway across the street from Kerry Park.

Meanwhile, construction has already started on a large new Kelowna Yacht Club facility down the road on the former site of the Water Street Senior's Centre across from the Kelonwa Community Theatre. Once that building is up and running, the city plans to demolish the existing yacht club building and expand Jim Stuart Park.

 

 

 

 

 

 

 

 

 

 

 

 

 

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

Flight4Life expects to break world record on Thursday
 
De Groot family outraged: Sister of dead Slocan suspect says police overreacted
 
Joanne Wilton Q & A
SHSS students perform Les Miserables
 
School District shifts major asset
 
East Kootenay schools get playground cash
Velma McKay and Vicky Dalton are Women of the Year
 
Lindley accepts Queens Jubilee medal
 
Japanese Consul General pays a visit to Sparwood

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 24 edition online now. Browse the archives.