Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

RCMP hunt for suspect in West Kelowna bank robbery

Suspect used a note and fled bank Saturday with an undisclosed amount of cash

Community Leader Awards: Shelley Pacholok

The Kelowna Capital News honours those who give back in the community

International Arts Festival returns to Kelowna

Living Things is a month-long festival with live performances by artists from around the world

Legion bell prank hits sour note

Anger erupts after Summerland Legion member removes bell from Peachland Legion

Kelowna Art Gallery members’ exhibition offers variety of media

Encounters will be held from Dec. 2 to Feb. 3

Vehicle with dog inside stolen from Oliver gas station

A black Honda CRV was stolen from the Oliver Chevron early Sunday morning

Team Canada loses 5-2 over the Czech Republic at World Junior A Challenge

Vees’ Tychonick drops in one of Team Canada West’s pair of goals

Site C decision coming Monday

Premier John Horgan to announce fate of dam project at B.C. legislature

PIGS bring Pink Floyd sound to Kelowna

Victoria band pays tribute to iconic British band on Feb. 10 at Mary Irwin Theatre

Letter: Another flagger dies; when will you slow down?

You have all seen our signs, trucks and my favorite our cones. Why don’t you slow down?

Kelowna-developed technology to be unveiled at Summerhill

Kelowna winery and tech company introduces new technology for phone or tablet

California couple name daughter after Revelstoke

Revy Elle Atashroo was born on Nov. 27. Her name honours the town her parents loved exploring.

Most Read