Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

The Okanagan may not get snow for Christmas

You may not want to bet on having a White Christmas

First candles lit to celebrate Hanukkah in Kelowna

The public menorah was lit to celebrate the holiday in Stuart Park

Outbreak at Okanagan hospital

Gastrointestinal illness reported at Vernon Jubilee Hospital

Kelowna public menorah lit tonight to celebrate Hanukkah

The menorah will be lit tonight after celebrations at 5 p.m. in Stuart Park

VIDEO: New series takes in-depth look at sexual harassment in B.C.

Black Press takes a hard look at sexual harassment in B.C.

Me Too At Work: Sexual assault and harassment in the B.C. workplace

Introducing an in-depth look at who is affected and what can be done

Warriors ground Rockets in Moose Jaw

Moose Jaw scores five in the third period to down Kelowna in Rockets’ third game of prairie road trip

Horgan says pot smokers may face same outdoor rules as cigarette smokers

B.C. is developing its rules on recreational marijuana

Dedicated volunteers look for clues

Police appreciate work of those who provide extra eyes for missing women investigations.

Truck driver volunteers to take dog lost in B.C. back home to Alberta

Frankie, a pit bull service dog, was found wandering in the Lower Mainland

B.C. teacher suspended after explicit images projected to class

Jeffrey Rohin Muthanna had been viewing porn on a school laptop for two years

Vernon Jazz Society swings into Christmas with holiday jams

Sandy Cameron’s Shujazz Sextet will be onstage at the Vernon Jazz Club Saturday, Dec. 16

Man who pledged to give B.C. hockey team millions charged with fraud

Mike Gould has since repaid $8,000 he allegedly owed Cranbrook restaurant, owner says

Most Read