Clearing work on the Site C dam project near Fort St. John, 2016. Work has gone on for two years, with $1.7 billion spent and more than 2,000 people working. (BC HYDRO)

UPDATE: Weaver’s claims of Site C road damage denied

BC Hydro says sweatlodge, burial ground accommodated

BC Hydro says a road realignment project to make way for the Site C dam on the Peace River would not “pave over” a sweatlodge and disrupt an aboriginal burial site, contrary to claims made by B.C. Green Party leader Andrew Weaver Wednesday.

BC Hydro issued a statement in response to Weaver’s claims, made after a tour of the area this week.

“We are aware of West Moberly and Prophet River First Nation’s concerns about construction activities in the Cache Creek/Bear Flat area in the vicinity of the sweat lodge,” the statement says.

“It is not true that we plan to pave over the sweat lodge. In response to the concerns from the West Moberly and Prophet River First Nations, we have refined the design of Highway 29 to increase the distance between the highway realignment and the sweat lodge. While we acknowledge that the sweat lodge would be in closer proximity to the new road, we determined that we could move the highway an additional eight metres to the north to accommodate planting vegetation or noise abatement measures on the south side.

“These measures would act as a buffer between the sweat lodge and the highway. The total distance from the centre line of the highway to the sweat lodge is now 45 metres. In addition, we are willing to discuss other mitigation measures in relation to the sweat lodge, including constructing a new spiritual centre or other additional cultural facilities elsewhere in the Cache Creek/Bear Flat area.

“Following extensive archeological work, BC Hydro has not confirmed any Aboriginal burial sites in the project area; however, we continue to listen and investigate specific sites as advised by First Nations communities.

“In March, the West Moberly and Prophet River First Nations notified BC Hydro of the location of a potential burial site. We have refined the design of Highway 29 to lengthen the bridge by 50 metres to avoid ground disturbance of this site, and raised the height of the bridge to provide about two metres clearance above the specific site to avoid disturbing the site.

“We are meeting with them this week to further discuss their concerns.”

Weaver spoke to reporters in Victoria after touring the area with the project’s most vocal opponents, leaders of the West Moberly and Prophet River First Nations and Ken and Arlene Boon, the farmers who have refused to move from the area affected by the construction and eventual flooding near Fort St. John.

“What’s remarkable about all of this is that there are a number of options for the road,” Weaver said. “They could continue building the road, but the road does not have to be the option that goes through the sweatlodge, through the Boons’ house and through another house down the road and across a burial site.”

The location of the sweatlodge is “new information,” Weaver said. He was not able to say how long it has been there.

Weaver reiterated the reasons why he wants the Site C project stopped, two years into construction with $1.7 billion spent and more committed to major earthworks and powerhouse contracts. He said he supported the original proposal in 2009 when the estimated cost was less than $6 billion, but now the cost is estimated at nearly $9 billion and he expects it to go higher.

Based on the higher cost, BC Hydro would lose money on power supply agreements with major liquefied natural gas producers that have yet to commit to construction, he said.

Premier Christy Clark made her own trip to Fort St. John this week, to meet with local B.C. Liberal MLAs and tout the employment benefits of the project. More than 2,200 people are working on the site, with a construction timeline leading to the dam coming online in 2024.

more to come…

Just Posted

Community Leader Awards: Sheila Gardiner-Watt

The Kelowna Capital News celebrates those in the community who go above and beyond

Mamas for Mamas founder survives with new lease on life

Kelowna’s Shannon Christensen escaped a dangerous situation and lived to tell about it

Announced this week in Kelowna

A listing of some of the events that were announced in the Kelowna area this week

Big White ski instructor named Top 10 in Canada

Big White’s Josh Foster has been selected for the Canadian Ski Instructors’ Alliance (CSIA) Interski team

Kelowna restaurant hosts popular New York Chef

Need something to do this Valentine’s Day?

REPLAY: B.C. this week in video

In case you missed it, here’s a look at replay-worthy highlights from across the province this week

Philadelphia Eagles headed to Super Bowl

After routing the Minnesota Vikings 38-7, they will face Tom Brady and the New England Patriots

Heavy snowfall closes Mount Washington on Vancouver Island

Road to ski resort deemed unsafe, vehicles buried under more than three feet of snow

VIDEO: Dramatic video shows return of rescued B.C. snowboarders

Two snowboarders were rescued near Rossland, B.C. on Sunday after being lost overnight.

Tom Brady leads Patriots back to Super Bowl, top Jaguars 24-20

New England to face winner of Sunday night’s game between Minnesota and Philadelphia on Feb. 4

Letter: Site C figures not correct

Kelowna letter-writer raises questions about the Site C dam project

Letter: Site C opponents are whining

If native treaty rights are being disrespected, just who is disrespecting them?

Albas: Canada Jobs program being politicized

Conservative MP Dan Albas’ weekly column takes on the student summer job plan

Fuhr: Pension for Life is a commitment to veterans

Kelowna-Lake Country MP Stephen Fuhr talks about his government’s commitment to veterans

Most Read