Clark warns of $600 million delay to Site C dam

NDP leader John Horgan says Clark’s claims ‘unsupported’

Premier Christy Clark has written to the NDP and Green Party leaders, warning that a delay in removing two homes from the path of a Site C dam road could delay the project by a year and cost as much as $600 million.

In letters released Tuesday, Clark asked both NDP leader John Horgan and B.C. Green Party leader Andrew Weaver to reconsider Horgan’s request to delay the removal of two homes on land expropriated by BC Hydro for the third dam on the Peace River.

A decision must be made by June 15 on whether to proceed, Clark wrote. Her letters also ask:

“…whether or not you would like government to issue a ‘tools down’ request to BC Hydro on the other decisions that are essential in maintaining the budget and construction schedule of the Site C Clean Energy Project, given that the project is likely to progress past the ‘point of no return’ before the B.C. Utilities Commission review you have suggested could be reasonably concluded.”

Horgan responded Tuesday, calling Clark’s claims of cost escalation “unsupported” and accusing the B.C. Liberals of driving up BC Hydro bills due to “mismanagement” of the project.

Weaver also responded to Clark’s letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.

Horgan wrote to BC Hydro CEO Jessica McDonald May 31 to ask for a lease extension for two families, including Peace Valley Landowner Association members Ken and Arlene Boon, whose homes are on a road right-of-way needed for the dam.

“I believe there is no demonstrated short-term need to force these families from their homes, and because the status of the next governments of British Columbia are uncertain, the threat of imminent removal of residents from their expropriated homes and property is unreasonable,” Horgan wrote.

Clark’s letter says “the relocation of the homes in question is necessary as part of a two-year road and bridge construction project that will enable river diversion to occur in September 2019.”

River diversion has to be done when water is low in summer, not in winter when the two existing Peace River dams are running water through turbines to supply winter electricity demand.

“Preliminary work undertaken on this issue by BC Hydro indicates that should river diversion not be completed as scheduled, a year-long delay would occur in order to divert the river during the next low-flow period, in September 2020,” Clark wrote. “This one-year delay is estimated to cost ratepayers $600 million.”

“Given the obligation that BC Hydro has in place with respect to road construction and completion, a decision to proceed will need to be made no later than June 15, 2017 in order to maintain the September 2019 river diversion schedule.”

Weaver responded to Clark’s letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.

Just Posted

Kelowna council settles on 3.6 per cent tax increase for 2018

“Safety” budget heavy on a wide-range of public safety related spending

Meningococcal disease outbreak declared in Okanagan

Five cases in last six months among 15-to-19 year-olds, including one in Coldstream

Mail bandit puts damper on Christmas in Central Okanagan

Mail Box thefts have been reported throughout the Okanagan

West Kelowna RCMP seeks to reunite stolen items to owners

Numerous personal belongings were found during a seizure

Budget 2018: Kelowna to look at monitoring downtown security cameras 24 hours per day

Potential $30,000 budget item will be discussed further over objections of the mayor

VIDEO: Average Canadian food bill to rise by $348 in 2018

Atlantic Canada and B.C. will see the most increases for consumers

Debt-to-household-income ratio rises in third quarter, household net worth

Total household credit market debt grew to $2.11 trillion in the third quarter

Charges in car wash shooting stalled

Court waits for police watchdog report on Salmon Arm incident.

B.C. Mountie told to resign after texting teenage sex assault victim

RCMP documents say Const. Brian Eden sent sexually inappropriate photos to 17-year-old girl

Family doctors should learn to treat addiction, not shun patients: scientist

B.C. Centre on Substance Use’s Dr. Evan Wood said efforts underway to change addiction medicine image

Four dog deaths investigated in Cranbrook

One vet suggests a parallel to these deaths and similar ones in 2016

Province rejects Ajax mine in Kamloops

KGHM Ajax had proposed a 1,700-hectare open-pit copper and gold mine, just southwest of Kamloops

Border officers rally at B.C.’s Peace Arch

CBSA employees tire of ‘lack of respect’

FCC votes along party lines to end ‘net neutrality’

Move rolls back restrictions that keep big providers from blocking services they don’t like

Most Read