An artist’s rendering of the Site C dam, the third hydro dam on the Peace River. BC Hydro image

Site C dam project plagued by problems: expert

E. Harvey Elwin expresses concern about internal BC Hydro and government documents

The mammoth Site C hydro-electric project is seriously behind schedule, plagued by quality problems and marked by secrecy, says an assessment by an international dam expert.

E. Harvey Elwin – hired by a First Nation asking for a court injunction to aspects of the dam’s construction – expresses concern about work at the job site in his 196-page report citing internal BC Hydro and government documents, many of them previously confidential.

“In my opinion, it is the sign of a large performance problem with the (main) contractor meeting the requirements of the specifications and quality of work,” he wrote in the report filed Wednesday in B.C. Supreme Court.

In a letter accompanying a progress report to the B.C. Utilities Commission dated July 11, BC Hydro president Chris O’Riley said the project remains “on time and within budget.”

Spokespeople for the provincial government and contractor Peace River Hydro Partners did not immediately respond to requests for comment.

Elwin, who has worked on dams around the world including China’s Three Gorges project, concludes the dam’s construction is likely to take years longer than BC Hydro says.

READ MORE: Anti-Site C petition approved

The 1,100-megawatt dam and generating station on the Peace River in northern B.C. would flood parts of the traditional territory of the West Moberly and Prophet River First Nations.

In January they filed a civil court case, alleging their rights have been violated.

West Moberly also applied for an injunction to halt construction pending the outcome of the rights case. That motion goes to court Monday. Elwin’s report was filed in support of West Moberly’s case.

BC Hydro has argued any injunction would create heavy budget overruns. It says a two-year injunction would cost an extra $660 million and a three-year stoppage would cost $1.1 billion.

Based on documents BC Hydro was forced to release as part of the court process, Elwin disagrees.

He found that stopping work in 13 areas the West Moberly are most concerned about would delay completion of major milestones by a few months at most. He concluded the cost of a three-year injunction would be $71 million.

Elwin expresses serious concern at the number of reports detailing construction problems.

“I have observed that there are always a large number of (non-conformance reports) generated and being processed. It is also evident that many are not closed rapidly,” he writes. “The number, frequency, and lengths of time to close (such reports) are an indicator of the quality of work.”

Projections for placing concrete are “overly optimistic and not realistically achievable,” he says.

Last year, Elwin says contractors placed 35 per cent of the concrete they were supposed to for a major section of the dam. At that rate, Site C will take well over a decade to finish, significantly past its 2024 completion date, Elwin suggests.

O’Riley’s letter acknowledges the project has had problems meeting its construction schedule. It has also had safety concerns.

He said an agreement has been reached with the main contractor that will accelerate some activities and provide incentive payments to meet deadlines. That’s projected to cost up to $325 million.

“While the agreement will draw on our contingency budget … we have been able to manage the costs within the existing construction budget,” O’Riley wrote.

Elwin is skeptical.

“I seriously doubt the capability of the (main) contractor to take on and effectively perform to an accelerated schedule,” says his report.

The Canadian Press

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Peachland photographer thankful for community support

‘I share my photos because I want others to enjoy Peachland too,’ Rhonda Johnson said

GoFundMe launched for man severely injured in Westside Road crash

Doctors say it could be 12 months before Tyler Sheriff is able to walk again

Lake Country man facing charges after bear mace incident

The 23-year-old man has since been released from police custody

Car drives into Peachland business

One staff member at the business suffered minor injuries

Peachland Farmers’ Market sees good turnout despite challenging times

Unpredictable weather and pandemic concerns aren’t stopping people from enjoying the market

Lower Mainland woman says llama farming neighbour shot her 11-month-old pup

Young dog was on owner’s Maple Ridge property when it was killed on June 21

B.C. records 31 new cases, six deaths over three days due to COVID-19

There are 166 active cases in B.C., 16 people in hospital

Police issue warning after baby comes across suspected drugs in Kamloops park

The 11-month-old girl’s mother posted photos on social media showing a small plastic bag containing a purple substance

B.C. highway widening job reduced, costs still up $61 million

Union-only project scales back work to widen Trans-Canada

Kamloops man pleads guilty in vehicle-ramming incident that injured a Mountie

Adam Hibbert was arrested following a collision during a police pursuit on May 26, 2019

Greater Victoria nanny pleads guilty to child porn, sexual interference charges

Johnathon Lee Robichaud pleaded guilty to slew of sex crimes

Most Read