An artist’s rendering of the Site C dam, the third hydro dam on the Peace River. BC Hydro image

Site C dam project plagued by problems: expert

E. Harvey Elwin expresses concern about internal BC Hydro and government documents

The mammoth Site C hydro-electric project is seriously behind schedule, plagued by quality problems and marked by secrecy, says an assessment by an international dam expert.

E. Harvey Elwin – hired by a First Nation asking for a court injunction to aspects of the dam’s construction – expresses concern about work at the job site in his 196-page report citing internal BC Hydro and government documents, many of them previously confidential.

“In my opinion, it is the sign of a large performance problem with the (main) contractor meeting the requirements of the specifications and quality of work,” he wrote in the report filed Wednesday in B.C. Supreme Court.

In a letter accompanying a progress report to the B.C. Utilities Commission dated July 11, BC Hydro president Chris O’Riley said the project remains “on time and within budget.”

Spokespeople for the provincial government and contractor Peace River Hydro Partners did not immediately respond to requests for comment.

Elwin, who has worked on dams around the world including China’s Three Gorges project, concludes the dam’s construction is likely to take years longer than BC Hydro says.

READ MORE: Anti-Site C petition approved

The 1,100-megawatt dam and generating station on the Peace River in northern B.C. would flood parts of the traditional territory of the West Moberly and Prophet River First Nations.

In January they filed a civil court case, alleging their rights have been violated.

West Moberly also applied for an injunction to halt construction pending the outcome of the rights case. That motion goes to court Monday. Elwin’s report was filed in support of West Moberly’s case.

BC Hydro has argued any injunction would create heavy budget overruns. It says a two-year injunction would cost an extra $660 million and a three-year stoppage would cost $1.1 billion.

Based on documents BC Hydro was forced to release as part of the court process, Elwin disagrees.

He found that stopping work in 13 areas the West Moberly are most concerned about would delay completion of major milestones by a few months at most. He concluded the cost of a three-year injunction would be $71 million.

Elwin expresses serious concern at the number of reports detailing construction problems.

“I have observed that there are always a large number of (non-conformance reports) generated and being processed. It is also evident that many are not closed rapidly,” he writes. “The number, frequency, and lengths of time to close (such reports) are an indicator of the quality of work.”

Projections for placing concrete are “overly optimistic and not realistically achievable,” he says.

Last year, Elwin says contractors placed 35 per cent of the concrete they were supposed to for a major section of the dam. At that rate, Site C will take well over a decade to finish, significantly past its 2024 completion date, Elwin suggests.

O’Riley’s letter acknowledges the project has had problems meeting its construction schedule. It has also had safety concerns.

He said an agreement has been reached with the main contractor that will accelerate some activities and provide incentive payments to meet deadlines. That’s projected to cost up to $325 million.

“While the agreement will draw on our contingency budget … we have been able to manage the costs within the existing construction budget,” O’Riley wrote.

Elwin is skeptical.

“I seriously doubt the capability of the (main) contractor to take on and effectively perform to an accelerated schedule,” says his report.

The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

NHL stars return to Kelowna for charity slo-pitch game

The Gorges/Comeau Homebase Chairty Tournament returns June 28

Motorbike rider taken to hospital following crash

The incident happened on Highway 97 near Leckie Road

Chilliwack man charged in crash that killed Kelowna pregnant woman

Frank Tessman charged for 2018 Highway 1 accident where Kelowna elementary school teacher died

Severe thunderstorm watch issued for Okanagan and Connector

Storms expected to develop this morning and intensify early in the afternoon

Kelowna RCMP launch crime reporting website

RCMP look to modernize police operations throughout the Okanagan

Suspicious Rutland car fire has one woman think it was targeted

A family who raised their voice against the McCurdy Road house has car torched, is it connected?

Olympic skier from B.C. suing Alpine Canada after coach’s sex offences

Bertrand Charest was convicted in 2017 on 37 charges

Action imperative on Missing and Murdered Indigenous Women and Girls

Chief commissioner into national inquiry encourages governments, private sector to act

B.C. senior’s car vandalized for more than 18 months

Retired RCMP officer determined to catch ‘tagger.’

VIDEO: Driver doing laps in busy Vancouver intersections nets charges

Toyota Camry spotted doing laps in intersection, driving towards pedestrians

COLUMN: Imagine the possibilities at the library

Programs at Summerland Library promote reading among children

Former Canucks goalie Roberto Luongo to retire

‘Bobby Lou’ calls it a career after 19 NHL seasons

Massive red treble clef proposed to take over Shuswap

Idea is to pay tribute to artisans in the community

Straight from Dehart

Restauranteur opens second business in Kelowna

Most Read