Wireless meters in test lab. BC Hydro is required to test meters annually to make sure they are accurately measuring electricity use.

Smart meter system finishes under budget

Officially complete for $777 million, wireless grid still needs rural extension using cellular networks to reach across B.C.

BC Hydro’s wireless grid system was officially complete at the end of 2015, with a total cost the Crown utility now projects to be $777 million.

That’s $153 million below the original budget, said Greg Reimer, executive vice president, transmission, distribution and customer service for BC Hydro. It includes all the elements required by the B.C. government when it ordered the installation of the smart meter system as part of its Clean Energy Act in 2010.

Reimer said in an interview the system has also exceeded the $70 million in savings projected for the first three years of operation.

“We’ve realized about $100 million in benefits during that time, particularly from operational savings,” Reimer said. “Customers are getting more accurate bills. We’ve reduced our manual meter reading reads and our bill estimates. Meter reading and billing is automated through the system.”

The smart grid had its severest test at the end of August 2015 when a windstorm brought down thousands of drought-weakened trees, leaving 700,000 customers on southern Vancouver Island and the Lower Mainland without electricity.

Power was restored to all areas in five days, which was half the time it took to recover from the December 2006 windstorm that flattened trees in Vancouver’s Stanley Park, Reimer said. The 2006 storm blacked out only half the number of homes of the 2015 event.

Reimer said the ability to test an entire power line after one break is repaired means the crew doesn’t have to drive the rest of the line, and can move to the next confirmed problem when repairing storm damage.

BC Hydro has defended its power theft savings after NDP energy critic Adrian Dix questioned them. In a recent letter to BC Hydro CEO Jessica McDonald, Dix said the company’s estimate of power theft by marijuana growers was “magically” inflated by then-energy minister Rich Coleman in 2006, then increased again in the utility’s 2011 business case for the wireless system.

[Dix letter here, Reimer response here]

Reimer said the business case projected a 75 per cent reduction in power theft, and the reduction for this fiscal year is projected at 80 per cent, as the smart grid detects actual power consumption and compares it to billed amounts.

While it’s officially complete, the smart grid requires ongoing maintenance and annual testing of meters to meet federal accuracy regulations. BC Hydro also plans to install more than 4,000 meters that use commercial cellular phone networks to send in readings.

Those are for locations with concrete basement meter rooms that can’t reach the grid, or rural areas where it is too expensive to extend the BC Hydro wireless grid, Reimer said.

There are still 13,320 BC Hydro customers who have refused to accept smart meters, opting to pay a monthly fee for manual meter reading of a mechanical meter or a wireless meter with the radio transmitter turned off.

 

Just Posted

Your Saturday story catch-up

Every Saturday, read our popular stories from the week

Friends of Gable Beach concerned with District of Lake Country’s proposal

Carr’s Landing residents oppose the district’s latest solution to Gable Beach

Greyhound stop in Oyama gets cut

Expanded regional transit replacement option for Lake Country

Heavy snowfall for Coquihalla

Kelowna - Snowfall is expected to continue on the highway until Sunday

Lake Country budget approved

Lake Country’s 2018 Operating and Capital Budget was approved Tuesday night

President praises nearly 1,800 volunteers at B.C. Games

Ashley Wadhwani sits down with the Kamloops 2018 B.C. Winter Games President Niki Remesz

How to keep local news visible in your Facebook feed

Facebook has changed the news feed to emphasize personal connections. You might see less news.

The way government learn someone has died is getting a digital overhaul

Governments in Canada turned to private consultants 2 years ago to offer blueprint

Bobsleigh team misses Olympic medal finish

Canadian team finishes four-man event 0.84 seconds behind first place, 0.31 seconds from podium

A most delicious competition at the Mall at Piccadilly

Salmon Arm hosts the Best of the Shuswap Pie Baking Contest

B.C. Games: Athletes talk Team Canada at PyeongChang 2018

From Andi Naudie to Evan McEachran there’s an Olympian for every athlete to look up to

Snowboarders sliding into fresh territory at B.C. Games

Athletes hit the slopes for first appearance as an event at the B.C. Winter Games in Kamloops

Looking back at the 1979 B.C. Games: Good memories, even better jackets

39 years later, Kamloops is hosting the Winter Games again, with some volunteers returning

OLYMPICS 101: Oldest and youngest Canadians to reach the podium

This year, Canada sent its most athletes in Winter Games history, here’s a look at record breakers

Most Read