Work to restart on Nancee Way underpass

With the Westside Road overpass repairs nearly complete, work on Nancee Way underpass is set to begin this week.

Crews work to put the finishing touches on repairs to the Westside Road overpass

West Kelowna residents may feel like they’ve entered a time machine.

In early November, 2011, work began on the Nancee Way underpass: The final piece of the $41 million Westside Road Interchange Project.

But the collapse of a retaining wall on the Westside Road overpass and four months of repairs has seemingly brought crews back to square one.

On Monday, the Westside Road overpass was reopened to the public.

Evelyn Lube, project communications director for the Westside Road Interchange Project said that work to the Nancee Way underpass will begin this week.

“We should see the remaining asphalt on the highway start to be excavated. Now that the repairs have been substantially completed, the contractor can focus on (the underpass),” said Lube.

The Westside Road Interchange Project website still indicates that the entire project is likely to be done by June, 2012; however, that seems unlikely, given the four month delay to work on the Nancee Way underpass.

“The contractor has focused their work on getting the repairs done. Now that those repairs are done, we will be pressing the contractor to complete their updated repair schedule.

“At this point, we’re not aware of any additional time that might be required. We understand from our contractor that they’re on board for a fall 2012 completion, but we’re still waiting for the final details of that.”

After the embarrassing result of the Westside Road overpass failure, Lube said that the contractor will “certainly” be taking measures to ensure that a similar result doesn’t happen to the Nancee Way underpass.

“Now that we’ve had this failure, there is attention on making sure that it doesn’t happen again.”

Lube noted that during the repairs to retaining walls on the Westside Road overpass, all of the failed rebar was replaced. The new rebar was tested and inspected to ensure that it is safe.

Although the Westside Road overpass is fully functional, there are still only two lanes of traffic flowing under the overpass in either direction. This is likely to be the case until early April.

“Two lanes each way will be in place for the next few weeks. Once they have the excavation done on the highway . . . then they’ll be able to extend that third lane.”

Minor repair work, which “doesn’t affect the safety of the structure” is still being done to the Westside Road overpass. Lube said that work should be done in the next couple of weeks as well.

In the coming days, traffic will be realigned to how it was before the overpass failure in November. That realignment will be in effect until work to the underpass is complete.

wpaterson@kelownacapnews.com

Just Posted

Two escape vehicle fire

Smoke and flames were spotted coming from the hood of a truck on Hudson Road

Kelowna motel robbed, suspect sought

The suspect threatened to harm the lone front desk clerk and demanded money.

Penticton reporter reflects on covering Charles Manson

Charles Manson, leader of a murderous cult, died on Sunday at 83

West Kelowna neighbourhood fed up with criminal activity

Prowler frustrating West Kelowna residents

Big White to send off Olympians in style

Okanagan ski resort picked as location for official send-off of Canada’s 2018 Winter Olympic team

Heavy snowfall expected on Coquihalla

Snow forecast for mountain highways

Hergott: A pedestrian’s legal obligation

Lawyer Paul Hergott questions the moral obligation of pedestrians and motorists

Coyotes grab Okanagan boys title

George Elliott defeats Seaton in AA volleyball final, seeded third heading to provincials

ICBC overbilling for crash repairs not the problem, dealers say

Collision repair shops reject union claim of inflated costs

Last day for shoeboxes at Kelowna Gospel Fellowship

Kelowna church has been gathering gifts for kids in need in countries around the world

Owls soar to Okanagan volleyball title

KSS girls win 4A championship for 12th straight year beating Pen Hi in final

B.C. groups to address child sex abuse in sports

viaSport is organizing a full day of education in association with Canadian Centre for Child Protection and the Coaching Association of Canada.

Report sets exercise guidelines for young kids, including ‘tummy time’ for babies

Kids aged one to four should get at least three hours of physical activity throughout the day

Stampeders return to Grey Cup with 32-28 win over Edmonton Eskimos

The Stampeders will face the Toronto Argonauts next Sunday in Ottawa for the title

Most Read